City Council - Public Works and Natural Resources Committee
Mon, June 1, 2026
City Council – Public Works and Natural Resources Committee — June 1, 2026
This was a regular committee meeting chaired by Councilmember Michael Lilliquist, with Councilmembers Jace Cotton and Lisa Anderson also serving on the committee. Two of the three originally scheduled items were heard; the third (an update on the Comprehensive Sewer Plan and Post Point solids handling technology) was removed from the agenda and rescheduled to a future meeting.
Tremont Lift Station Contract Award (Project EU193)
The committee considered awarding a construction contract to build a new lift station at the corner of Meridian Street and Tremont Avenue in North Bellingham, along with a new sewer force main connecting northward to the existing system between Horton Road and Van Wyck Road.
Assistant City Engineer Mike Wilson and Project Engineer Kyle Carlson provided background. They explained that the Meridian Street gravity sewer line recently completed ends near the Walmart at Van Wyck Road. North of that, the terrain crests a small hill and drops into a separate basin that cannot gravity-flow into the sewer system — hence the need for a lift station and force main to pump sewage back to the existing network. Once complete, the project will allow existing city properties on the west side of Meridian to connect to sewer, and will lay the groundwork for future connections serving properties to the east and north, including areas contemplated under the long-discussed Meridian Kline/Kelly annexation area and the "Kay-Tech" properties up toward Larson Road — all consistent with the city's Comprehensive Plan.
The new lift station will include two pumps with physical space reserved for a third to accommodate future growth. The force main consists of six-inch and eight-inch lines, sized to meet Comprehensive Plan capacity projections. The project also includes a new fiber line to support SCADA (remote monitoring) systems and off-site environmental mitigation work at the Baker Creek open space site off Northwest Drive.
The city received five bids; Tiger Construction Ltd. submitted the lowest responsive bid at $3,058,400.30 including sales tax, coming in below the engineer's estimate of approximately $3.3 million. The project includes an apprenticeship hour requirement. Construction is expected to run from July 2026 through approximately April 2027.
Councilmember Anderson asked about potential traffic impacts during construction, particularly given the high traffic volume on Meridian Street and proximity to summer events like the Linen Fair. Staff indicated that most of the work will be concentrated at the lift station site itself, with only one roadway crossing at Tremont for the force main, and that detailed scheduling will be worked out with the contractor. Staff acknowledged that road work would likely occur later in the construction timeline, which Anderson noted she hoped would mean after peak summer traffic.
Councilmember Lilliquist asked whether the force main piping was sized to handle a potential third pump if capacity needs increase. Staff confirmed the design meets all Comprehensive Plan projections for the area.
Vote: Anderson moved approval; Cotton seconded (implied by unanimous "aye" vote). The motion passed unanimously (3–0) and will be forwarded to the full council with a positive recommendation.
Pine Street Crossing Grant Agreement with WSDOT (Project WF023)
The committee considered authorizing the mayor to enter into a Local Agency Agreement with the Washington State Department of Transportation (WSDOT) to formalize federal grant funding for the Pine Street railroad crossing project. The project will upgrade the crossing to quiet zone standards (which would allow trains to pass without sounding horns), add a multi-use trail crossing, upgrade utilities, and improve the Pine Street and Cornwall Avenue intersection.
Engineering Manager Freeman Anthony explained that the city secured two federal funding sources: Section 130 railway safety grant funding and recently unobligated regional carbon reduction funds. The availability of the carbon reduction funding prompted the city to "federalize" the project process now — rather than waiting until the construction phase — to take advantage of the opportunity. The Local Agency Agreement is a standard procedural requirement to receive and administer federal transportation funds through WSDOT.
Total project cost is estimated at $2,765,200. The federal grant award is $950,000. The remaining funding — approximately $1.4 million from local Real Estate Excise Tax funds and $465,000 from the local transportation fund — is already budgeted and requires no budget amendment.
Councilmember Anderson offered no questions but expressed enthusiasm, noting she can hear train horns from her home on the far side of Sehome Hill and is eager to see quiet zone designation move forward.
Vote: Anderson moved approval; the motion passed unanimously (3–0) and will be forwarded to full council with a positive recommendation.
Key Takeaways
AI-generated summary from voice-to-text transcript. Not the official record. Verify important details with the source documents linked above.
What happened at this meeting
A contract award for the Tremont Lift Station, project EU193, Bid No. 19B-2026
Staff presented a contract award recommendation for the Tremont Lift Station project (EU-193), which will expand the sewer system in North Bellingham by constructing a new lift station at Tremont Avenue and Meridian Street with related force main infrastructure. Tiger Construction Limited submitted the lowest responsive bid of $3,058,400.30, below the engineer's estimate of $3.3 million, with construction scheduled from July through April and apprenticeship hour requirements included. Councilmember Lillquist raised concerns about roadway work timing during high-volume periods such as Linen Fair and summer months, and staff indicated that detailed scheduling would be coordinated with the contractor, with initial work focused on the lift station area. A council member also questioned the capacity of the six-inch and eight-inch force mains for potential future pump additions, and staff confirmed the piping is designed to meet all areas referenced in the comprehensive plan. The motion to award the contract passed unanimously with a positive recommendation to the full council.
An agreement with the Washington State Department of Transportation for grant funding for the Pine Street Crossing, project WF023
Agenda items (3)
What happened
# Summary: Tremont Lift Station Contract Award (Project EU193, Bid No. 19B-2026)Staff presented a contract award recommendation for the Tremont Lift Station project (EU-193), which will expand the sewer system in North Bellingham by constructing a new lift station at Tremont Avenue and Meridian Street with related force main infrastructure. Tiger Construction Limited submitted the lowest responsive bid of $3,058,400.30, below the engineer's estimate of $3.3 million, with construction scheduled from July through April and apprenticeship hour requirements included. Councilmember Lillquist raised concerns about roadway work timing during high-volume periods such as Linen Fair and summer months, and staff indicated that detailed scheduling would be coordinated with the contractor, with initial work focused on the lift station area. A council member also questioned the capacity of the six-inch and eight-inch force mains for potential future pump additions, and staff confirmed the piping is designed to meet all areas referenced in the comprehensive plan. The motion to award the contract passed unanimously with a positive recommendation to the full council.
What happened
Staff presented a local agency agreement with the Washington State Department of Transportation for grant funding for the Pine Street crossing project (WF-023). Engineering Manager Freeman Anthony explained that the project received both federal Section 130 railway grant funding and recently unobligated regional carbon reduction funding, which prompted them to federalize the process now rather than waiting for construction. Council member Lisa expressed enthusiasm for the quiet zone standards and multi-use trail crossing improvements, noting she can hear trains from her home. The motion to authorize the mayor to enter into the agreement passed unanimously; the grant amount is $950,000 with a total project cost of $2,765,200, with remaining funding from local real estate excise tax and transportation funds already in the budget.Additional votes recorded in minutes
Award contract for Tremont Lift Station project (EU-193, bid 19B-2026) to Tiger Construction Limited
Authorize mayor to enter into local agency agreement with WSDOT for Pine Street crossing grant funding (WF-023)
Verbatim transcript available
47 transcript segments indexed